![]()
| Entertainment | Government | |||
| Technology | Utilities | |||
| Internet Service Provider | Banking | |||
| Manufacturing | Insurance | |||
| Hospitals | Education | |||
| Health Care Administration |
Worldwide Feature Animation Company
Project: 8500 sq.ft. Data Center
Project Value: $ 2,144,000.00
Scope of Work: Design, engineer and
provide construction administration for a new 8500 sq. ft. Data Center and ancillary
facilities.
Challenge: The customer wanted maximum flexibility to wire, cable, set,
and move equipment with the ultimate amount of seismic capacity within the Data
Center.
Engineering: To that end, RSFT developed an understructure that the computer
racks could sit on top of - actually floating above the raised floor.
Construction: A heavy metal structure was created that could hold the
equipment, yet be flexible enough to move in the event of an earthquake. Along
with a structural engineer, a sliding grid system was developed that would move
in an x and y axis to accommodate all Moves, Adds and Changes. The raised floor
was built around this grid and built to meet all seismic criteria. The customer
also required a monitoring system that would allow them to view and control
each installed device-so that processes could be controlled from a remote location.
This Data Center had to be up and running while the actual building was also
going up. Construction was completed on time and RSFT assisted with transition
and move planning.
Internet Service Provider
Project: 3500 sq.ft. Data Center
Project Value: $ 648,000.00
Scope of Work:
Design, engineer and build three new Data Centers in Phoenix, Los Angeles and
San Jose, including interior design and space planning for computer operations
rooms, printer rooms, and communications rooms.
Challenge: Build a Data Center from which Internet Service Providers could
"rent" space, so that each individual ISP could capitalize on standby generation,
access control, central monitoring and fire suppression--without making an investment
in their own facility.
Construction: The customer had made commitments to move customers into
these facilities in three cities (Phoenix, Los Angeles and San Jose) within
a 16 week timeframe. Each facility was in a high-rise building, which was a
challenge, especially for fire suppression. RSFT built all three facilities
on time and each is now 80% occupied, including one of the major Internet Search
engines.
Project: Three 3500 sq.ft. Data Centers
Project Value: $ 3,210,000.00
Scope of Work: Design, engineering and
construction to install a mission-critical internet co-location facility.
Challenge: To build a new Data Center in 16 weeks. In order to meet this
tight time line, RSFT was given the authority to move forward without much customer
contact.
Construction: RSFT had to design and build, as well as obtain approval
from the city of Scotts Valley - concurrently--in order to meet this very aggressive
timetable. In addition, the fire suppression system required needed to be upgraded.
RSFT worked closely with the fire department and the fire Marshall to obtain
approval and meet the delivery date.
Worldwide Semiconductor Chip Manufacturer
Project: 30,000 sq.ft. Data Center
Project Value: $12,500,000.00
Scope of Work: Data Center consulting
and engineering services to 34 campus data centers and design and construction
of one 30,000 sq. ft. facility with 2x redundancy.
Challenge: RSFT was contracted as a consultant to help them understand
what their deficits were within their thirty-four distributed data centers across
the Intel campus.
Consultation: Over an 18 month period each data center was audited and
recommendations for changes and corrections were made, and a central monitoring
system was put in place.
Construction: Intel decided to consolidate these data centers and requested
a plan for a 30,000 sq.ft. facility that would be built in one of their existing
buildings. Intel mandated 2x redundancy (for example, three generators providing
one function), for each system (fire suppression, power distribution, all transmission
media, etc.). This was a very complex infrastructure to protect their vital
information. The customer had calculated that if their data center went down
it would cost them $1 million per minute. This facility was completed and supports
a fabrication plant in Santa Clara.
Project: 2,500 sq.ft. Data Center and Cold Site
Project Value: $ 670,000.00
Scope of Work: Design and construct
a computer disaster recovery center which featured a 600 sq. ft. "hot site".
Design and construct a 2,500 sq. ft. Data Center/Cold Site.
Challenge: The customer's "Recover-all" program required an operational
data center to be constructed in a remote location that was safe from earthquake
or fire damage. This Data Center would then be offered to their customers in
the event that the customer had a disaster and needed to relocate to a safe
facility. This facility had to be robust enough to handle any kind of hardware,
software, or personnel.
Construction: RSFT built this facility with a number of offices for personnel
relocation, as well as the capability to handle any kind of hardware -- and
be up and running within a 24 hour period.
Major Semiconductor Chip Manufacturer
Project: Communications
Infrastructure
Approximate Value: $225,000
Design and implementation of an AT&T structured cabling system for the customer’s new consolidated headquarters ---a three building, multiple floor complex. Connect three buildings and multiple floors via fiber optic cable to create one Local Area Network for more than five hundred and seventy five (575) work stations. Include a paging network in the design and implementation of structured cabling system. Complete design and implementation of the structured cabling system in conjunction with the compressed five month master construction and relocation schedule. Design and implement a structured cabling system to support the customer’s voice and data requirements for two Colorado and one Texas office. Provide a five (5) year Performance Warranty for completed installations.
University Medical Center
Project: 7000 sq.ft. Data Center
Project Value: $ 1,268,000.00
Scope of Work: Design, engineer, complete
construction documents and build a 7,000 sq. ft. Data Center Processing Facility
and ancillary facilities.
Challenge: Bring multi-function operations into one central location
in the basement of the hospital.
Discovery: The project began with analyzing
dependency, adjacency, personnel access and work flow requirements to develop
a variety of designs that would meet the customer's needs.
Engineering: The Data Center was designed to include a Situation Room
for personnel to meet in the event of a disaster; a Printer and Document Reproduction
room, where a high volume of paperwork would flow including all patient records;
a Mail Box Transition Area to keep the Document Room secure; a Tape Library
and back-up room which would be secured by a two hour environment in the event
of a fire; a Staging Area for new computers and software that allowed access
from the data center, as well as vendors.
Construction: Both noise abatement and dust control were carefully addressed.
RSFT worked with the hospital engineering staff to ensure the existing infrastructure
did not have loss of utility to the rest of the hospital. The move of all computer
equipment to the new data center was planned to occur within a 2 hour timeframe
- since the computer equipment monitored patient functions as well as critical
records. RSFT trained the facilities department on the new Data Center and continues
to support them with moves, adds and changes as the Center evolves.
Hospital Computer Center
Project: 12,000 sq.ft. Data Center
Project Value: $ 1,025,000.00
Scope of Work: Design, engineer, complete
construction documents and build a 12,000 sq. ft. Data Center and ancillary
facilities. This included interior design and space planning for a computer
operations room, CPU room, printer room, media distribution room, situation
room and communications room.
Challenge: Move from an in-hospital Data Center to an off-site Data Center.
An in-hospital Data Center is bound by ASHPOD, which can almost double the cost
of construction due to seismic requirements. However, an off-site computer room
creates media transmission issues between the Data Center and the remote hospital.
This Data Center was built with redundancy of transmission media in order to
ensure an uninterruptable connection with the hospital. It is extremely robust
and includes a Standby Generator as well as underground fuel tanks. RSFT designed
it to operate indefinitely, regardless of outside influence or events.
Clinic
Project: 600 sq.ft. Data Center
Project Value: $ 225,000.00
Scope of Work: Design, engineering and
construction of a 600 sq. ft. Data Center. Challenge: This very unique Data
Center required that it be built with no raised floor, and with everything distributed
overhead with racks-into cabinets and relay racks.
Construction: This data center needed to be able to handle any kind of
equipment, in either racks or cabinets. All data communication would run overhead
in a grid system. The Data Center also had to be able to run as a remote facility.
RSFT created a rack and cabinet environment with a remote monitoring system.
Health Care Administrator
Project:12,000 sq.ft. Data Center
Project Value: $ 1.5 million
Scope
of Work: RSFT was commissioned to act as architect and engineer to provide
complete construction documents for a new 3,000 sq.ft. Data Center that would
reside at the hospital.
Documentation: RSFT provided a full set of specifications for each infrastructure
item: architectural, mechanical, electrical, structural and fire suppression.
Consultation: The customer sent the RSFT specifications out for bid and
RSFT reviewed and interviewed all contractors, as well as making the recommendations
for who was to build the project. Construction: RSFT supervised the build-out
of the data center to ensure that all contractors met the design drawings and
specifications.
Health Care Administrator
Project: 3000 sq.ft. Data Center and 1200 Data Communications Stations
Project Value: $ 590,000.00
Scope of Work: Complete design, engineering
and construction of a 3,000 sq. ft. Data Center.
Challenge: To move from a 1,000 sq. ft. computer room space into a new
building. The original computer room was highly disorganized, had cables everywhere,
computers stacked, and was at high risk for disaster. This was primarily due
to very rapid growth and lack of planning.
Consulting: RSFT provided a planning, transition and growth model for
a 3,000 sq.ft. Data Center with a wiring and management scheme that allowed
for Moves, Adds, and Changes without recreating the disorganized, high-risk
environment they had started with.
Major Defense Contractor
Project: 2,800 SF Data Center
Project Value: $ 360,000.00
Scope of Work: Design and construction
of a 2,800 sq. ft. Data Center.
Challenge: RSFT was tasked with building a room that would house equipment
that tested micro chips to military specifications. This equipment (Trillium
Units), had to be in a cleanroom environment, as the environment itself could
not affect test results.
Construction: This was a fast track project that required design, construction
and submissions for project approval to happen simultaneously.
Major Gas & Electric Utility
Project: Communications
Infrastructure
Approximate Values: $750,000
As the preferred communications vendor, furnish multiple services to support information systems requirements at more than twelve administrative and industrial sites. Create an "island of automation" for more than one thousand eight hundred (1,800) six-plex work stations. Modify customer’s design to implement a structured cabling system that links a four (4) building campus with single- and multi-mode fiber optic cable, voice trunk cable, and an IBM Type I redundant Token Ring system. Design and construct cable pathways to comply with EIA/TIA specifications and support over 1 million feet of horizontal cable. Create a "quality program" to test and certify the structured cabling system so the customer could relocate more than one thousand eight hundred (1,800) work stations without failure. Produce soft copy "as-built" information that allows customer to administer and perform adds, moves, and changes cost effectively for the various information platforms. Communications services included installing electrical, conduit, fiber optic cable, IBM cabling, Category 5 unshielded twisted pair (UTP), and coax cable.
Banking
Major Southwest Bank, Merger/Acquisition
Project: Communications
Infrastructure
Approximate Value: $250,000
Place and certify digital network interface equipment to support connectivity of remote controllers, terminals, and printers. Set-up a temporary staging facility to receive equipment, burn-in equipment to detect infant mortality, configure equipment for network compliance, produce asset deployment report, and retrieve de-installed equipment for shipping to third party vendor. Install horizontal cabling to support the installation of new POS equipment at each branch. De-install existing branch equipment and re-install, over a weekend flash cut-over, new IBM 4700 equipment at the forty two (42) branches. Programming and installation responsibilities for this project included the digital network interface equipment, remote controllers, terminals, and printers. The key functions required for the remote site work were: project management, site audits, staging (receiving configuration, testing, shipping), network hardware installation, and system acceptance.
Major Southwest Bank, Conversion to Digital Network
Project: Communications
Infrastructure
Approximate Value: $200,000
Coordination of network equipment delivery and disbursement to approximately one hundred and fifty (150) branches and thirty (30) real estate loan offices throughout Arizona. Project responsibilities include the coordination of circuit installations, circuit verification, and trouble resolution with local common carrier. Installation of DSU/CSU equipment and performance testing of network in preparation of Teller POS and ATM platform cut-over. Cutover POS and ATMs to new digital network. Provide central site and remote site technicians for cut-over and certification of the Teller and ATM platforms to the new digital network.
Major Northern California Bank, Acquisition
Project: Communications
Infrastructure
Approximate Values: $325,000
Support acquisition network requirements for approximately ninety branches. Place and certify digital network interface equipment to support connectivity of remote controllers, terminals, and printers. Set-up a temporary staging facility to receive equipment, burn-in equipment to detect infant mortality, configure equipment for network compliance, produce asset deployment report, and retrieve de-installed equipment for shipping to third party vendor. Install horizontal cabling to support the installation of new POS equipment. De-install existing branch equipment and re-install, over a weekend flash cut-over, new IBM 4700 equipment at the ninety branches. Programming and installation responsibilities for this project included the digital network interface equipment, remote controllers, terminals, and printers. The key functions required for the remote site work were: project management, site audits, staging (receiving configuration, testing, shipping), network hardware installation, and system acceptance.
Major Northern California Bank, ATM Network Conversion
Project: Communications
Infrastructure
Approximate Value:$420,000
Participate in the project to implement and complete the cut-over of more than two thousand (2,000) ATMs to the new OSPF network within a six month period. Technical implementation included the configuration and deployment of the 3Com201 Branch Boundary Router for redundancy and the installation of the Hypercom equipment for Protocol conversion. Cut-over the entire population of bank ATMs to the Open Net platform in four (4) months. The conversion of the ATMs involved programming and installing Protocol conversion equipment, cabling, and the cut-over of Boundary Routers and ATMs.
Research Institute
Project: Communications
Infrastructure
Approximate Value: $76,752
Design a structured cabling system, including recommended installation criteria, for the future implementation of the 43,500 square foot facility. Responsible to furnish all material, labor, installation, testing, and project management for project. Design and implement an AMP Netconnect System. Includes providing Category 5 patch panels for the 10-Base T connectivity, Category 5 horizontal data cabling installation, Category 3 horizontal voice cabling installation, installation of copper voice and fiber optic data backbone system, administration for station terminations, labeling, validation, and warranty.
Major Insurance Company
Project: Communications Infrastructure
Approximate Value: $154,341
Provide the installation, labeling, testing and warranty for an AT&T Integrated Premises Distribution System (PDS). The system supported analog and digital voice applications, data, local area networks (LAN), video and low voltage devices for building controls and management on a common cabling platform.
Northern California University
Project: Communications Infrastructure
Approximate Value: $239,984
Install a new Technology Center Communications Distribution System providing inside plant multimedia voice, data, and video carrying capabilities for the new library, as well as wide area networking into the local community. The new Technology Center is the center of the largest Community College District in the country. Provide all coordination, labor, materials, testing, cutover, record documentation, and certification necessary for the turnkey inside plant installation: Library (intra-building) cable plant including MDF, IDF, and raceway construction; riser and station copper and fiber optic cabling, including a telecommunications grounding sub-system. Provide all coordination, labor, materials, testing, cutover, record documentation, and certification necessary for the turnkey Tie Cable inter-building installation: fiber optic backbone cable connecting the existing Mainframe room to the Library Switch room. The distribution system and its supporting infrastructure was designed to be sufficiently flexible to insure the greatest number of communications alternatives to accommodate a life span exceeding present and planned equipment. The data networks were configured in a physical hierarchical star topology with three hierarchical levels: system, riser, and station, with interconnections required between hierarchical levels. The fiber-based data riser system is a non-dedicated star topology. The fiber backbone cable is a non-dedicated point to point inter-building connection. Provided operational documentation to include a detailed Project Schedule from contract award to acceptance testing of the System. This schedule was reviewed and updated to reflect actual production on a weekly basis.